The Fire Retardant Paint Process Explained: 12 Steps from Site Assessment and Application to FS251 Electronic Certificate

Once you have decided to apply fire retardant treatment to false ceilings, timber partitions or curtains, the next questions are usually: "How does the whole process work? What do I need to prepare? When will I receive the FS251?" Fire retardant paint work may look like ordinary painting, but every step, from assessment, material checks and surface preparation to application control, certificate issuance and submission, affects whether the work will pass Fire Services Department (FSD) inspection. This guide breaks the full process into 12 steps and explains each party's responsibilities and the new arrangements following the move to electronic FS251 certificates in 2026.

Quick answer: The basic process is for a Class 2 Registered Fire Service Installation Contractor to assess the materials, confirm the use of a product accepted by the Director of Fire Services, apply it according to the product requirements before the materials are painted or assembled, and then, within 14 days of completion, prepare, electronically sign and submit the FS251 through the FSD's online system. From 1 July 2026, the FSD only accepts FS251 certificates submitted electronically, and certificates carry an anti-counterfeit QR code.

Contents

  1. Process overview
  2. Who is responsible for what
  3. Before the work: steps 1 to 5
  4. During the work: steps 6 to 9
  5. After the work: steps 10 to 12
  6. New arrangements for electronic FS251
  7. How to verify contractors and certificates
  8. Handover checklist
  9. The most common problems in the process
  10. Frequently asked questions

1. Process Overview

The fire retardant treatment process can be divided into three stages, before, during and after the work, with 12 steps in total:

StageStepMain responsibility
Before the work1. Confirm FSD requirementsOwner / tenant
2. Compile a material list and existing reportsOwner, fitting-out contractor
3. Site assessmentRegistered contractor
4. Confirm quotation and productOwner, registered contractor
5. Coordinate the work scheduleFitting-out contractor, registered contractor
During the work6. Surface preparationRegistered contractor, fitting-out contractor
7. Brushing or sprayingRegistered contractor
8. Drying and follow-on workRegistered contractor, fitting-out contractor
9. Work recordsRegistered contractor
After the work10. Completion checkRegistered contractor, owner
11. Issue and submit the FS251Registered contractor
12. Filing documents and FSD inspectionOwner / licensee

If you are not yet clear on what fire retardant paint does and which materials it suits, start with What Is Fire Retardant Paint? Principles, Types and Hong Kong Fire Safety Requirements. For material standards, see BS 476 Part 7 Class 1 vs Class 2.

2. Who Is Responsible for What

Many delays happen because each party assumes "the other side will handle it". The table below sets out each party's responsibilities in a typical project:

RoleMain responsibilities
Owner / tenant / licenseeUnderstand the FSD's written requirements, appoint a qualified contractor, provide premises information, keep certificates and test reports, and ensure any alterations during the licence period also comply
Fitting-out contractorProvide material specifications and test reports, schedule time for fire retardant treatment, avoid painting relevant materials before treatment, and coordinate work times
Class 2 Registered Fire Service Installation ContractorAssess materials, select products accepted by the Director of Fire Services, apply them according to product requirements, issue the FS251 and send a copy to the FSD
FSDSet fire safety requirements, review documents and carry out inspections

The most critical coordination is the sequencing of work between the fitting-out contractor and the registered contractor. If the fitting-out contractor has already painted the timber, it becomes difficult to treat, and the whole process has to go back a step.

3. Before the Work: Steps 1 to 5

Step 1: Confirm FSD Requirements

Start by checking the written requirements issued by the FSD or the licensing authority to confirm which items need treatment. Fire safety requirements differ between restaurants, tutorial schools, places of amusement and other premises. Within the same letter, false ceilings, partitions, wall finishes and curtains may also be listed separately. Do not rely on a verbal understanding; work from the documents. For the legal background, see Hong Kong Fire Safety Laws and Regulations.

Step 2: Compile a Material List and Existing Reports

List all combustible fitting-out materials in the premises and record for each one:

Materials that already have a valid test report, with the product and installation method matching what is on site, may need no treatment; simply keep the report as proof. Doing this step well directly reduces the treatment area and cost.

Step 3: Site Assessment

During a site visit, the contractor will generally check the following:

  1. Whether the materials are suitable for treatment and whether the surface allows the product to adhere or penetrate
  2. The actual area, by measurement
  3. Ceiling height and whether high-access equipment is needed
  4. On-site ventilation, power and water supply
  5. Whether the premises is open for business, and available working hours
  6. Whether other fire service installations need to be handled at the same time

If materials are already painted or have unsuitable surfaces, the contractor will recommend removing the coating, replacing the material, or switching to a material with a test report.

Step 4: Confirm the Quotation and Product

When confirming the quotation, make sure the following are clearly stated:

For quotation items and cost factors, see How Much Does Fire Retardant Paint Cost in Hong Kong?.

Step 5: Coordinate the Work Schedule

Fire retardant treatment should be scheduled after the materials are assembled but before painting or surface finishing. It is generally advisable to book about 2 to 3 weeks in advance. The fitting-out contractor should allow for this stage in the works programme and confirm the following with the registered contractor:

4. During the Work: Steps 6 to 9

Step 6: Surface Preparation

The result depends heavily on the surface condition. Typical preparation includes:

For fabric, confirm that it has not been waterproofed or given a stain-resistant treatment, otherwise the fire retardant solution cannot penetrate the fibres.

Step 7: Brushing or Spraying

The contractor will choose brushing, rolling, spraying or misting depending on the material and product. During application, the following must be controlled according to the product instructions:

Control itemWhy it matters
Coverage per square metreWith insufficient coverage, the treated material may not reach the required class
Number of coatsSome products require several coats, each reaching the specified coverage
Interval between coatsApplying the next coat before the previous one is dry can affect adhesion and performance
Coverage of all areasCorners, edges and back faces are easily missed
Environmental conditionsTemperature, humidity and ventilation affect drying time

Different products have different coverage and coat requirements. Always follow the product instructions rather than relying on experience with ordinary paint.

Step 8: Drying and Follow-On Work

After treatment, allow the drying time specified for the product. If a topcoat or decorative finish is to be applied over the fire retardant paint, confirm that the topcoat is compatible with the fire retardant product and apply it as required, so that it does not affect how the fire retardant layer performs under heat. This should be agreed in advance between the registered contractor and the fitting-out contractor, not decided by the painters on their own.

Step 9: Work Records

A well-run contractor will record details of the work, such as:

These records help with later inspections and give the owner a basis for confirming that the work is complete. Owners can ask the contractor for work photos for their files.

5. After the Work: Steps 10 to 12

Step 10: Completion Check

After the work is done, the contractor should check that all areas have been treated and confirm this with the owner or fitting-out contractor. The owner can check each location and area against the original material list.

Step 11: Issue and Submit the FS251

Under section 9(1) of the Fire Service (Installations and Equipment) Regulations (Cap. 95B), a Registered Fire Service Installation Contractor must, within 14 days of completing the relevant work, issue the FS251 to the person who instructed the work and send a copy to the FSD. From 1 July 2026, the FS251 must be prepared, signed and submitted electronically through the FSD's online system, as explained in the next section.

Step 12: Filing Documents and FSD Inspection

After receiving the FS251, the owner should file it together with the following documents:

These can then be produced immediately for FSD inspection or licence renewal. If materials are changed during the licence period, recheck them and keep the new documents too.

6. New Arrangements for Electronic FS251

In mid-2026 the FSD launched an upgraded online submission system for the Certificate of Fire Service Installations and Equipment (FS251). From 1 July 2026, it only accepts certificates prepared, signed and submitted electronically, replacing paper submission.

Main Changes Under the New Arrangements

ItemNew arrangement
PreparationContractors enter certificate details directly into the online system, including the building address, type of fire service installation, inspection results, defects and repair status
SigningElectronic signature using "iAM Smart" or a Hongkong Post e-Cert
SubmissionSubmitted directly through the system, with data sent to the FSD in real time
Certificate formatAfter successful submission, the system automatically generates a formal electronic certificate with an anti-counterfeit QR code
Statutory deadlineUnchanged: issued and copy sent within 14 days of completing the work

What This Means for Owners and Tenants

7. How to Verify Contractors and Certificates

Verifying the Contractor

The FSD website has a "Registered Fire Service Installation Contractor (RFSIC) list search", where you can search by contractor name, registered address or registration number. Class 2 contractors have registration numbers beginning with "RC2". Before appointing a contractor, ask for the registration number and check against the list:

  1. Whether the contractor name matches the quotation
  2. Whether the registration class includes Class 2
  3. Whether the registration is still valid

Verifying the Certificate

After receiving the FS251, check the following details:

8. Handover Checklist

At completion, owners can confirm each item on this checklist:

Item to checkConfirmed
All materials needing treatment have been treated, with locations matching the list□
Treated area matches the quotation□
Name and information of the product used have been received□
Before and after photos have been received□
FS251 was issued within 14 days□
Address, work description and contractor details on the FS251 are correct□
Certificate carries an anti-counterfeit QR code□
Contractor verified as a Class 2 registered contractor□
Test reports, certificate and invoice have been filed□

9. The Most Common Problems in the Process

Problem 1: Arranging treatment after materials are painted

This is the most common and most expensive mistake. Once materials are painted, fire retardant products struggle to adhere or penetrate, and the coating often has to be removed or the material replaced. The solution is to list fire retardant treatment in the fitting-out programme as a designated step before painting.

Problem 2: Reports that do not match materials on site

If the model, thickness or installation method in a supplier's test report differs from what is on site, the report will not be accepted at inspection and fire retardant treatment will have to be done after all. Check reports at the procurement stage; see how to check a BS 476 Part 7 test report.

Problem 3: Missing some areas

For example, the walls are treated but the private room partitions or curtains are missed. Compiling a complete material list at step 2 avoids this problem.

Problem 4: Altering materials after treatment

Adding to, sanding or repainting materials after fire retardant treatment may make the original treatment ineffective. Consult the contractor before making changes.

Problem 5: Booking only when the inspection is near

Without enough lead time, the contractor may not be able to fit you in, or a rush surcharge may apply. Plan the timing of fire retardant treatment at the design stage.

Key Process Points for Different Premises

Premises typeKey process points
New restaurantsAlign with the licensing timetable, complete treatment before painting, and arrange it together with other fire service installations
Licensed premises in operationWork outside opening hours, treat in stages, and protect existing furniture and equipment
Exhibition boothsFit in with build-up times, and confirm the organiser's requirements and certificate submission deadline early
Schools and clubhousesAvoid class or activity times, and handle large areas of fabric and partitions

If your premises also needs its annual fire service installation inspection, see our Complete Guide to Fire System Maintenance and FS251 Annual Inspection. For other fire service installation and improvement works, see our Fire Engineering Services.

10. Frequently Asked Questions

How long does fire retardant paint work usually take?

It depends on the area, material, number of coats and drying time. Small shops or booths can generally be completed fairly quickly, while large-area or high-ceiling projects take longer. For booking, it is generally advisable to allow about 2 to 3 weeks in advance.

How soon after completion will I receive the FS251?

Under section 9(1) of Cap. 95B, the registered contractor must issue the FS251 within 14 days of completing the work and send a copy to the FSD. You can confirm the actual timing with the contractor when appointing them.

What has changed with the FS251 from 2026?

From 1 July 2026, the FSD only accepts FS251 certificates prepared, signed and submitted electronically by contractors through its online system. Contractors sign using "iAM Smart" or a Hongkong Post e-Cert, and after successful submission the system generates an electronic certificate with an anti-counterfeit QR code.

How can I confirm that a contractor is a Class 2 registered contractor?

Use the "Registered Fire Service Installation Contractor (RFSIC) list search" on the FSD website to search by contractor name or registration number. Class 2 contractors have registration numbers beginning with RC2.

Can the premises stay open during fire retardant paint work?

It is generally advisable to carry out the work outside opening hours, to avoid affecting customers and staff and to give the materials enough time to dry. Discuss the specific arrangements with the contractor.

Can a topcoat be applied over fire retardant paint?

Some products allow a compatible topcoat, but it must be applied according to the product requirements so as not to affect the performance of the fire retardant layer. The contractor should confirm the type of topcoat and application method.

If treated materials are later sanded or repainted, do they need retreating?

Sanding, repainting or altering materials may make the original fire retardant treatment ineffective. Consult the contractor before making changes; depending on the situation, retreatment and a new FS251 may be needed.

What documents should owners keep?

Keep the FS251 electronic certificate, material test reports, product information, quotation, invoice and work photos, ready to produce for FSD inspection or licence renewal.

Arrange Fire Retardant Treatment and FS251

Grand United Eng., Co. is a Registered Fire Service Installation Contractor in Hong Kong. We can handle the full process from material assessment and work scheduling to certificate submission, and coordinate with fitting-out contractors to reduce rework and delays. When you contact us, please provide the premises use, a material list, site photos, the fitting-out programme and any FSD letter of requirements. You can also browse our Project Cases, Service Coverage and FAQ.